Hi,

When we create a planned order in APO we are getting 2 Que generated in R/3. One for creating the Planned Order and the Other for changing the Planned Order. Interesting factor is the 2nd Que which changes the Planned Order deletes the Negative Component. Can any one please let me know why is it first of all triggering 2 Que in R/3 (Create and change) rather it should be only one for create planned order.

Thanks & Regards,

Praveen.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Pablo Moraes
Feb 08, 2017 at 04:19 PM
1

Hi Praveen,

Could you please detail the steps that you are taking until the moment you see these 2 queues?

Are you first creating the order, saving it and after that changing it and saving the prod. view again? Or is it just the order creation that is triggering 2 queues to be created?

I would suggest to check the parameters maintained for the block sizes definition in APO (//CP3).

Thanks and regards,

Pablo