Maintenance Order Dates different than operation dates

Hi all,

I have searched numerous threads for Basic start data and finish, but i have not find any solution to the following issue:

I have an order type with forward scheduling and in creation i give as start i,e 10.04.16 and finish 20.04.16.

However, the operation date takes as basic start and finish the current date and not the header dates.

I have gone through thread FAQ: Maintenance Order Scheduling but no solution.

Can you please help me.

BR

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

7 Answers

  • avatar image
    Former Member
    Apr 18, 2016 at 08:47 AM

    Hi Ali,

    Operation dates will change once you define the work, also on the operating time of work center.

    If your work center operation time is 8h, work define for operation as 10h then Operation Start Date will be today's date and Ende Date will be tomorrow's.

    Regards,

    Sunil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Alexandros Ntais

      Hi Ali,

      Your operation dates will change to as per Basic Date once you save the order. Automatic Scheduling should be active in configuration for Plant and Order Type combination ( T code: OPU7). If not then manually schedule the order.

      Regards,

      Sunil

  • Apr 18, 2016 at 10:04 AM

    Hi,

    The settings for my order type are:

    Is it possible operation to take header start and finish date?

    BR


    Scheduling.jpg (39.9 kB)
    Add comment
    10|10000 characters needed characters exceeded

  • Apr 18, 2016 at 11:04 AM

    Hi,

    I did by it did not work.

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 18, 2016 at 11:52 AM

    Here are my data';

    header.jpg

    I want automatically start of operation date to be the bsc. Start.

    BR


    item.jpg (48.2 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Hi Ali,

      I am not really sure but Could you please try by unchecking the " dafault current date as basic date for your particuar Plant in following customizing path.

      PM-CS - Maintenance and Service Orders - General Data - Activate Default Value for Current Date as Basic Date.

      Regards,

      Amol

  • Apr 18, 2016 at 01:47 PM

    Hi Amol,

    It is unchecked.... 😔.

    BR

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Ali,


      " Default current date as Basic Date. This setting will not affect, you have to maintain Basic Start Date manually then.

      In my system your scenario is working fine with below setting.

      Not sure what you have missed. Please share your Header screen shot.

      Regards,

      Sunil

      Capture.PNG (7.7 kB)
  • Apr 20, 2016 at 07:12 AM

    Hi all,

    I believe it has something to do with the scheduling. Here are my screens:


    header2.jpg (8.0 kB)
    item.jpg (48.2 kB)
    Add comment
    10|10000 characters needed characters exceeded

  • Apr 27, 2016 at 07:17 AM

    Hi Paul,

    Indeed in the scheduling it shows current date.

    Actually with the below settings

    i managed to handle it.

    but what only capacity means? what is the general impact?

    BR


    sch.jpg (46.1 kB)
    sett.jpg (41.3 kB)
    sch.jpg (46.4 kB)
    Add comment
    10|10000 characters needed characters exceeded