CJ30 Budget based on only Cost Plan Values

Hi All,

My client wants to do CJ30 only by copying the Plan Values and not direct input of budget amount.

Can we achieve in standard?

Regards,'

Suman

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Apr 18, 2016 at 06:32 AM

    Hi,

    Yes know about this.

    I want to restrict to use this method only. User cannot directly go and put a budget amount.

    He can only have to copy.

    Regards,

    Suman

    Add comment
    10|10000 characters needed characters exceeded

    • You can create a custom role and put CJ30 budget values only in display mode.

      Assign relevant user IDs this role. Its a simple way to utilize roles and authorizations in PS

      Your Basis consultant can help you in this.

      Shubham

  • Apr 18, 2016 at 06:30 AM

    hello

    This is very much a standard practice in SAP PS.

    Please follow below steps :

    1. You can copy the cost plan of CJ40 in to budget CJ30
    2. Go to CJ30 & open your project
    3. Select all WBS : Edit ->click on copy view -> select planned total
    4. Maintain % if required.

    This will copy the cost plan value in budget.

    Regards

    Shubham

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 18, 2016 at 06:32 AM

    Alternate option is T code IMCCP3 - Transfer planning cost of CJ40 to CJ30.