Mass Change of PM Orders' settlement Rules

Team,

We have a requirement of changing settlement rules in PM orders. This has been necessitated by the fact that equipment maybe utilized in more that one area, which would have different cost centers. The requirement is that costs get apportioned to all the cost centers where the equipment was utilized. This can only be achieved by .making changes to settlement rule by including all the cost centers. how do i go about making mass changes to the settlement rules if i have a lot of PM orders?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Apr 15, 2016 at 06:33 PM

    Hi,

    my opinion

    1) Easier - LSMW (Or other tools)

    2) ABAP

    PS: IW38 > mass change - isnĀ“t possible

    Dimas Faria

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 15, 2016 at 07:21 PM

    HI Mutale,

    Check transaciton :KOSRLIST_OR.

    With this you can get a list of orders with current settlement rule assigned. Then you can use LSMW to mass change with new values.

    Regards,

    Amol