Color in time sheet calendar not working correctly in ESS

Hello Experts, I have an issue related to Time Recording Calendar in ESS. The leaves should be highlighted in Green in Time Sheet Calendar. But its not happening correctly. An employee applied leave for 29th March 2016 to 11th April 2016. The leaves got posted in infotype 2001. But in calendar the leaves are not reflecting in green. I have also confirmed that there are no public holidays during this period. When the leaves are entered separately for each date in infotype 2001 i.e individual record for 29th, 30th, 31 likewise till 11th April then I am able to view green color for the dates in time sheet calendar. Please find the screenshot in attachment.

Capture.PNG (109.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Apr 16, 2016 at 06:51 AM

    Please can you help me resolving the issue.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 17, 2016 at 10:36 AM

    Hello Experts , Can you please help with the resolution for this isue.

    Regards,

    Vandana

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 18, 2016 at 01:12 PM

    I have also observed that this is happening only for one particular work schedule.

    Regards,

    Vandana

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 19, 2016 at 08:42 AM

    Hi Siddharth,

    Please find the CAC1 configuration in the image below. Need your guidance to resolve the incident.


    CAC1_1.png (51.1 kB)
    cac1_2.png (59.7 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • if its occuring only with personal work schedule? can you check again ie absences, CATS profile and calendar dates etc. i havent yet seen the scenario

      for testing scenario, assign teh employee work schedule which works and check if the absence is reflected correctly and then you can confirm