Schedule line Quantity missing for PO with custom UOM

Hi Gurus,

We have one custom UOM " SET " in ECC which is replicated to SNC as well.

But when I am creating a PO for the material having unit " SET " it is going to SNC but requested Schedule quantity is showing as " ZERO ".

There is no error message coming in this regard but quantity is missing.

Please let me know how to resolve this issue?

Regards,

Uday

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 15, 2016 at 10:05 PM

    What is the ISO Code mapped to SET?

    Regards,

    Niranjan

    Add comment
    10|10000 characters needed characters exceeded

    • IDocs uses ISO Code mapping before passing the UOM to SAP Netweaver/XI. If this mapping is missing I am not sure what UOM is going into the XML. Can you check what is being received as UOM in Replenishement OrderĀ  Notification XML. Also check base UOM of the material, SNC always shows Quantity in Base UOM.

      Regards,

      Niranjan