Copy data from Planning Area to Other.

Hi Experts

I am using SAP 2 and SAP 4 model in IBP- S&OP.

Is there a way I can copy the Consensus demand data from SAP 2 model to SAP 4.

In SAP 4 model I will be doing the Supply planning.Demand input I get from SAP2.

Please let me know your suggestions.

Regards

Roshan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 15, 2016 at 07:07 AM

    Hi Roshan,

    You may check the below thread with similar query-

    Copy SAP2 Master & Key Figure Data Across P... | SCN

    Thanks,

    Rohit

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 15, 2016 at 11:33 AM

    Hi Roshan,

    Usually you don't split the processes in separate planning areas unless each has a different model structure and they don't require immediate integration. If you use the standard planning areas then SAP4 is already part of SAP2. So why to split? In SAP2 you can very easily have an end to end simulation.

    However, if this is your requirement, you can create an outbound job via HCI to export demand data from PA1 and an Inbound one to upload it into PA2.

    Regards

    Alecsandra

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Roshan

      In addition if you observed any specific supply KF like Independent demand, coverage etc that is not in PA SAP2 then you can create it manually in SAP2 ( referring to SAP4 PA)

      It will be best as explained by Alescsandra that try to manage business process in one PA

      Regards

      Anil