Hello,

I have two materials A and B that have the same component C. After the MRP runs it shows only the dependent requirements for material A and not for B,I need for both to appear

Any ideas?

Thank you,

A

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

What does the MRP list (MD07) tell you? Maybe you had stock at the time it ran. Maybe you have no planning file entry the material that was not planned.

You also did not answer if you have any other fields in the MRP views different.

Former Member
0 Kudos

In MD07 it appears like this

The materials are the same in all MRP tabs

Former Member
0 Kudos

I did found stock at that time,

Thank you so much for your help

Answers (7)

Answers (7)

Former Member
0 Kudos

The demand is set automatically by the system,like in the first material I didn't create a planned order or anything that will generate the demands.

And I've checked the materials are not components on another BOMs,they are new created materials

JL23
Active Contributor
0 Kudos

Sorry that is nonsense - SAP does not propose anything to order just because you have a material master or a BOM.

You need demand, either planned by yourself, from forecasting or coming from orders to enable MRP to plan a material and to create planned orders (if they are not created manually).

So just click the detail icon in front of the PldOrd and there the button for pegged requirements to know why you got a planned order.

Former Member
0 Kudos

Ok,I understand now, so it seems for that material a planned order was created

Former Member
0 Kudos

But that selling material has in its BOM both materials

6000042940 and 6000043205 and still the requirements appear only for one of them

JL23
Active Contributor
0 Kudos

Oh I was confused - now I see, 1000042501 is the component and 6000042940 and 6000043205 are the material to be produced.

So where is your demand for 6000043205 which should trigger that its BOM is considered in the MRP run?

I think you should look for BOMs where 6000042940 and 6000043205 are components so that they get planned.

JL23
Active Contributor
0 Kudos

Compare all fields in your 4 MRP views and list what fields have different values.

Show screenshots of the BOM for both materials.

Former Member
0 Kudos

In MRP 4 view both material have the same values. Nothing different.

BOM for material A

Bom Material B

The highlighted material is the component C. That doesn't appear in both material requirements MD04

Former Member
0 Kudos

Material A with component C "Dep Req"

and Material B without component C

In Material Master both of A and B have the same characteristics. I really don't know where the problem is

Former Member
0 Kudos

Is it possible the requirements are actually there, just collapsed under material A? Please check the 'Disp. All Rqmnts Individually' button.

mangesh_p
Explorer
0 Kudos

Check Stock material B. If stock is more than demand, it will not pass dependent requirement to component C.

Former Member
0 Kudos

Stock is 0 on both materials A and B

Former Member
0 Kudos

Check the BOM of material B for the production relevancy, bulk settings, and validity dates of component C. Also check the MRP type of material B.

Former Member
0 Kudos

Thank you Aaron for your input

But I've checked all all of the materials A and B looks the same,also the BOMs ,are identically. The components is production relevant.the validity it's ok.