on 02-07-2017 1:57 PM
Hello,
I have two materials A and B that have the same component C. After the MRP runs it shows only the dependent requirements for material A and not for B,I need for both to appear
Any ideas?
Thank you,
A
What does the MRP list (MD07) tell you? Maybe you had stock at the time it ran. Maybe you have no planning file entry the material that was not planned.
You also did not answer if you have any other fields in the MRP views different.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The demand is set automatically by the system,like in the first material I didn't create a planned order or anything that will generate the demands.
And I've checked the materials are not components on another BOMs,they are new created materials
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry that is nonsense - SAP does not propose anything to order just because you have a material master or a BOM.
You need demand, either planned by yourself, from forecasting or coming from orders to enable MRP to plan a material and to create planned orders (if they are not created manually).
So just click the detail icon in front of the PldOrd and there the button for pegged requirements to know why you got a planned order.
Oh I was confused - now I see, 1000042501 is the component and 6000042940 and 6000043205 are the material to be produced.
So where is your demand for 6000043205 which should trigger that its BOM is considered in the MRP run?
I think you should look for BOMs where 6000042940 and 6000043205 are components so that they get planned.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Compare all fields in your 4 MRP views and list what fields have different values.
Show screenshots of the BOM for both materials.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is it possible the requirements are actually there, just collapsed under material A? Please check the 'Disp. All Rqmnts Individually' button.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check Stock material B. If stock is more than demand, it will not pass dependent requirement to component C.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the BOM of material B for the production relevancy, bulk settings, and validity dates of component C. Also check the MRP type of material B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.