Hi All,

I want to check capacity of my internal activity for which I have assigned workcentre on that activity.Formula which I'm using capacity is 'SAP008' After assign hours to activity, when I run 'CM05' report for Overload and 'CM01' for Load, I'm not getting desired result as I have assigned assign many hours beyond available hours.

Below is the screen shot of workcentre and others:

For capacity check on network:

Hour assigned on activity

After scheduling when I run 'CM05' capacity overload, I got this error message

I have also run 'CM01' Capacity Load report so it's showing me only operating hours.

So kindly guide me where I'm missing to get desire result.

Regards,

Faizan

Work_Center_UP.png (48.8 kB)
CJ20N.png (46.6 kB)
Activity_Hour.png (41.6 kB)
CM05.png (14.9 kB)
CM01.png (18.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Apr 13, 2016 at 09:12 AM

    Hi Faizan,

    Can you please check at the network header level for these activities if capacity planning is checked or not?

    Regards

    Sammar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 13, 2016 at 11:43 AM

    Hi All,

    Can anyone answer my question?

    Regards,

    Faizan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Shubham Srivastava

      Hi Shubham,

      I have check points which you have highlighted:

      • Check in SPRO in scheduling parameter for the order type , whether you have checked the capacity check box "Generate capacity requirement"
        • In control key of network, 'Determine capacity requirement' check is enable.

      • Check in WC in scheduling tab , the formula has been assigned and the control key assigned to routing has checked for capacity requirements.
        • For PS WC scheduliing tab, there isn't any formula for work centre category '0006'.

      • In project planning board , select edit -> Functions->Activate capacities
        • Already activated but still no effect getting same message.

      • Also , make sure that the amount of required work is specified (not the duration).It should be directly below the WC. The formula specified in WC creation /change will create capacity requirements and the work gets distributed as per the formula.
        • I have assigned work specified and on the basis of that work, duration is calculated automatically by selecting calculation key 'Calculate duration'.

      So after doing that, still I'm not able to view result in 'CM05' report.

      Regards,