Is there a way to allow only one CO object - Cost center OR Order

We are facing problems with interfaces when there are postings with CO object costcenter and also an internal order. Is it possible to prevent this happening with customizing?

Thank you!

Add comment
10|10000 characters needed characters exceeded

  • Hello Manfred,

    Have you check and matched Field Status Group (FSG) at both ends of Interface module. Any field mismatch in both will clash. Activate either Cost Centre or Orders fields for certain nature of expenes.

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 07, 2017 at 03:39 PM

    Hi,

    You can create a validation in OKC7, allowing only one cost object to be introduced.

    Regards,

    Eli