Hi Gurus,

I have this scenario:

1. There is a project (SAP - PS) with row materials in Project Stock.

2. We create a Production Order, and comsume row materiales from Project Stock.

3. Production Order delivers a Finished Product in Project Stock.

I would like to know if Material Ledger can calculate Actual Cost by Plant + Project Stock + Finished Product?

Is there a standar scenario to this casuistic?

Thanks in advance.

José Luis

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 13, 2016 at 03:10 AM

    Hi Jose

    Yes. This is covered in standard solution itself.

    It should work

    Ajay M

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 14, 2016 at 05:21 AM

    Hi Jose

    So far I understand for any material you can have a one standard cost across system and you can't get different standard cost at diff application area like PS level etc..

    Kamal