Actual Cost by Plant + Project Stock + Material

Former Member
0 Kudos

Hi Gurus,

I have this scenario:

1. There is a project (SAP - PS) with row materials in Project Stock.

2. We create a Production Order, and comsume row materiales from Project Stock.

3. Production Order delivers a Finished Product in Project Stock.

I would like to know if Material Ledger can calculate Actual Cost by Plant + Project Stock + Finished Product?

Is there a  standar scenario to this casuistic?

Thanks in advance.

José Luis

Accepted Solutions (1)

Accepted Solutions (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi Jose

Yes. This is covered in standard solution itself.

It should work

Ajay M

Former Member
0 Kudos

Hi Ajay,



Thank you for your response.


Then, I understand that:



1. The same Finished Good (3S),  in the same Plant, in different Project Stock, I would have different actual cost.



I would like to know if is possible calculate Standard cost by Plant + Project Stock and Material.



Thanks in advance for your help.



Atte.

José Luis

ajaycwa1981
Active Contributor
0 Kudos

Hi

Std cost is always at Material Level (Ck11n). It's not at project level

If you are in complex MTO scenario, then you can calculate Planned cost at project level. But std cost always at Mat level

Answers (1)

Answers (1)

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi Jose

So far I understand for any material you can have a one standard cost across system and you can't get different standard cost at diff application area like PS level etc..

Kamal