Hi Gurus

I have problems when transporting an environment. When transported gave me the error the Entity dimension,

"Hierarchy PARENTH1 needs to be deleted; transport dimension ENTITY"

So to solve the problem, I delete the hierarchy in QAS and I transport again and pass without error

I working SAP BPC 10.1 NW

Please Helps

Regards,

Nayadeth Jeldres

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

ok, and your question is?

0 Kudos

Every time when I transport, I have to delete the hierarchy in QAS, It is not overwriting. The hierarchy is empty. This should not happen

harsha_jalakam
Active Contributor
0 Kudos

I think it needs to be deleted first and then moved to Quality, to get your issues corrected for the new transports. Below is the reference link, please check slide 28&29
.http://a248.g.akamai.net/n/248/420835/bc30b8bb5fbea65ba5e33710cfbdc943eeb39512e48ce0d8639cc7246bbedd...

Former Member
0 Kudos

Hi Nayadeth,

How was parentH1 created in the entity dimension in QA? from transport?

Are you doing anything in the BW backend on the hierarchy?

also you don't need to include ENTITY dimension when you transport every time.

if you don't have much data in QA then you can try Harsha's suggestion, delete the whole environment then transport from dev again.

what is your BPC patch level?

Andy

0 Kudos

I do the transport as document, but I do not think it should eliminate the hierarchy every time I transport, should override

0 Kudos

How was parentH1 created in the entity dimension in QA? It was created in BPC


Are you doing anything in the BW backend on the hierarchy? Nothing only en SAP BPC


also you don't need to include ENTITY dimension when you transport every time. yes, but still worng the transport


if you don't have much data in QA then you can try Harsha's suggestion, delete the whole environment then transport from dev again. I did, but when I try transport the second time, again gave error in the hierarchy. transportation works, the hierarchy works if is not in bpc qa


what is your BPC patch level?


CPMBPC8100008SAPK-81008INCPMBPCSAP Business Planning and Consolidation


SAP BUSINESS PLANNING AND CONS10.5sap.comSAP PC 10.1 FOR SAP NW


Regards,

thanks boys

Nayadeth Jeldres



Former Member
0 Kudos

Hi Nayadeth,

Do you have any member formulas in the entity dimension?

Andy

harsha_jalakam
Active Contributor
0 Kudos

Sorry I meant to ask if you have done the transport of the deleted object in deletion mode or if you had done transport in deletion mode, are you still facing the issue

Former Member
0 Kudos

Hi Nayadeth,

In my experience, 10.1 does not like PARENTH1 to be empty.  Why would it be empty anyway?  Put something in it and test transport again.  If this fixes the issue, start using PARENTH1 and adjust as necessary.

Regards,

Di~An