Import and launch capacity leveling data from a legacy system

former_member223087
Participant
0 Kudos

Hi,

We are facing a situation with our customer where I would need your help.

This process is as follow:

Sales orders are created in SAP.

MPS is triggered manually, creating planned order with capacity requirements.

These requirements and dates (operations and order) are extracted from SAP to an external (company built) capacity analysing tool.

From this tool we will receive a list of orders/operations with new dates and possibly new duration.

We would like to import these changes in SAP as we would have done it with transaction CM31. I've seen the exit CY190001 which can be used when running it.

Does anyone think this is possible? how? Maybe by means of CM40?

No way to use APO.

Thanks in advance for any help.

Regards

Olivier

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member223087
Participant
0 Kudos

this is not very encouraging ...