Skip to Content
avatar image
Former Member

Error in routing creation

Hi Experts,

Good Day!

While creating routing for a material I am getting the error message which shown in the below screen shot.

Can any one suggest what corrective active I should take to solve this

Thanks in Advance.

Regards,

BLESSING

123.png (18.1 kB)
124.png (4.1 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Apr 08, 2016 at 11:47 AM

    Hello

    Check if the cost center is correctly assigned on the work center and if it is valid on the routing date.

    BR
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 08, 2016 at 12:50 PM

    Hello,

    You have to assign the cost center to the activity type in KP26.

    You can see what is the activity type in the work center in CR03.

    Kind Regards,

    Mariano

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 10, 2016 at 10:40 AM

    Hello,

      You have to maintain relation between Cost center activity as activity rate in KP26.

    Using this system will calculate  activity cost for that operation.

    Regards,

    Velmurugan S

    Add comment
    10|10000 characters needed characters exceeded