Skip to Content

How to distribute the changed route details in EWM to ECC outbound Delivery.

Hi Experts,

In our Outbound process the Route will not coming from ECC outbound delivery. We manually assign the Route in EWM and the same route information should be updated back to ECC outbound delivery.

Is there any specific config to allow the route information from EWM to ECC outbound delivery updation.

How is it possible. Kindly let me know please.

Thanks & Regards

Ramesh.R

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Apr 11, 2016 at 06:42 AM

    Dear Ramesh ,


    Since Creation of delivery is initiated at ERP will it be logical to have routes assigned to delivery at ECC before distributing to EWM.  Is there is any specific rationale  as why you are assigning route in EWM side ?

    Thanks

    Jinoy

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Jinoy

      In ERP Outbound Deliveries are created in advance.

      Business does not have idea of the route at that point of time.

      So they would like to assign the Route in EWM system

      Regards

      Ramesh.R

  • Apr 20, 2016 at 04:05 PM

    Hi!

    EWM transferred route to ERP  in BAPI_OUTB_DELIVERY_CONFIRM_DEC structure:

    HEADER_DATA_SPL-GEOROUTE.

    Check in smq2.

    BR, Alex.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 20, 2016 at 05:02 PM

    Dear Ramesh.R,

    please also see

    You can either:

    a.) determine or enter Route in ERP. Then this is NOT changeable in EWM

    b.) determine or enter Route in EWM. But then this route is NOT transferred back to ERP.

    What was describe above as GEOROUTE is a separte field which is only used for CRM processes. But this field is not the route which you will see in ERP as route on the delivery.

    I also wonder why you would need the route in ERP. Either the route is relevant in ERP then I would assume that you determine it there. Or it is not and it is only relevant for EWM then you determine it there but then why would you need it in ERP?

    Best regards

    Markus

    Add comment
    10|10000 characters needed characters exceeded