Equipment PRT with stock

Former Member
0 Kudos

Hi Experts,

I want to carryout following with PRT.

1. PRT to be required in stock , having its multiples (Serial or batch) at different locations viz. shopfloor, vendor etc.

2. Usage to be tracked.

How to achieve both.

Thanks in advance.

Regards,

Upendra

Accepted Solutions (1)

Accepted Solutions (1)

former_member189817
Active Contributor
0 Kudos

Hello

  You create  PRT as non valuated material with serial number with serialization level 1. So that you can keep it in stock as well can use of equipment status functionality .

Regards,

Velmurugan S

Former Member
0 Kudos

Dear Velmurugan,

I am able to track stock serially. But for tracking usage how its to be done?

Ex. I have one PRT having three multiples (3 serial nos.) Now at the time of confirmation how to capture, that on  which serial no. production was carried out so that its usage can be tracked.

Regards.

Upendra

former_member189817
Active Contributor
0 Kudos

Hello

Using user status for equipment ,you can track the usage.To set this user status,we need to use user exit.

Regards,

Velmurugan S

former_member195779
Active Participant
0 Kudos

Hi Upendra,

You can use measuring document for PRT functionality here to track the usage.

In this as soon as confirmation is done PRT usage is posted. Those you can see in IK17 tcode.

Follow the process to do PRT confiramtion in order

1.Craete an equipment with category P(PRT)

2.Create characteristics with UOM similar to the unit of production confirmation unit

3.Creating Measuring points and counter for the equipment

4.Create one measurement document with minimum reading to activate it(with 1as reading)

5.Creating a Maintenance Task List

6.Creating a Maintenance Plan

7.Attaching a Maintenance plan and measurement point to PRT Equipment.(here in equip[ment useage formula for PRT SAPF02 should be given)

8.Change Routing and assign PRT Equipment to Operation

9.Create Production order(Transaction Code:CO01)

10.Confirmation of Production Order(Transaction Code:CO15)

11.Check the measurement document list using IK17

Please see prt confirmation in production order | SCN .

Regards,

Amarnath Dube

Answers (0)