Planned Value / Actual Value not updated in Service entry sheet

Dear Experts,

Please advise why Planned Value / Actual Value are not updated in service entry sheet  (New Process) while it is updated in Project and sales order.

Thank you,

Best Regards,

NoMi

Plan Actual.JPG (49.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 19, 2016 at 01:55 PM

    Dear All,

    The Plan, Actual values and %  is updated on the planned order. When a service entry sheet is created (via new process or old process) the planned order (OBOS or OBSS) will get updated and you could see the details in that document. The service entry sheet will not show the values. This is how the programs were designed.

    Best Regards,

    NoMi