Issue in data transfer from MP3 to SAP

0 Kudos

Hi Experts,

For header material (819872-0001) data properly transferred from MP3 to SAP.

The problem arises at the item level


On March 31st, the Dep Req of week 14 + 15 +16 are gathered together. Then on April 4th, it is the one of 17,  on April 11th, etc………

Can any one plz explain y the Dep Req are gathered together in Item level?

What could be the reason for this?

Thanks in Advance.

Regards,

Blessing

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member195779
Active Participant
0 Kudos

Hi,

Can you also check if there is BOM explosion type relevant to collective requirement maintained @ item level of BOM.

Regards,

Amarnath Dube

0 Kudos

Hi Amarnath Dube,

     There is no any BOM explosion level maintained.

Regards

BLESSING

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

This is according to the system standard design. Even when using lot sizing procedure EX, requirements on the same day will generate a single purchase requisition.

Check the following information provided on FAQ note 550568:


Question:

There are several requirements on one day. Is it possible that the MRP creates a separate procurement proposal for every requirement?

Answer:

Same as for the daily lot size with a number of periods = 1 (lot size TB), requirements of one day are also grouped into one procurement proposal for the lot-for-lot order quantity (lot size EX) (see documentation for the lot-for-lot order quantity). Separate procurement proposals can be achieved only if you work with make-to-order production. Here, the requirements are managed in separate planning segments of the stock/requirements list.

On the document there is a solution for this issue using a BAdI. I have never tested it, but it should work.

Regards
Caetano

former_member201849
Contributor
0 Kudos

Hi Blessing

The reason might be you could have activated 2 in Individual/Collective Requirements field in MRP 4 View of the dependent Material.

Regards

Suresh.M

0 Kudos

Hi Suresh,

Individual/Collective requirements not maintained for that material.


Regards,

Blessing

former_member201849
Contributor
0 Kudos

Hi Blessing

What is the Lot Size you are using?

Regards

Suresh.M

0 Kudos

Hi Suresh,

Lot-for-lot order quantity has been maintained for header material.

Regards

Blessing