How to set a Chain in "completed" status when a step is in error status.

Hi All,

how is it possible to set a Chain in "completed" status if the chain is stopped because a step is in error status.

More exactly I want to avoid to execute all steps and "reset" the status of the Chain as "Completed", if this is possible.

I'm using Redwood 9.0.13.1

Any help will be greatly appreciated.

Thanks in advance for your kind support.

Regards,

Giovanni

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Apr 21, 2016 at 05:05 AM

    Hello Giovanni ,


    In order to keep the Job chain set to completed status even if a step or a job is in Error Status.

    go to Definitions --> Job Chains --> Right click on job chain and select edit mode.

    In Job chain edit window , Select the particular Step which you want to Mark as complete even its ended with Error. After you select the Step . On the Right side pane, there will be a field called " Final Status Handlers " . In that field you can set the status as per your requirement.

    In the above screen shot of edit mode job chain window, You have selected the Job Chain box , that's the reason you were unable to see Final status Handlers on the right side pane.


    Capture.JPG (107.9 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 13, 2016 at 11:03 AM

    Hello Nanda,

    Thank You for your reply. I have been trying to set/change the status but without success.

    I have followed these steps

    I find this context

    Thanks in advance for your kind support.

    Regards,

    Giovanni


    pastedImage_0.png (17.1 kB)
    pastedImage_3.png (22.0 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 31, 2016 at 02:03 PM

    Hello,

    Add a final status handler, GoTo end of chain on status Error.

    Regards Gerben

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 02, 2016 at 09:59 AM

    Hello Giovanni,

    As suggested by Gerben, this can be achieved using the Status Handlers on Steps under the chain.

    If you choose the Status Handler "On Error" /"On Killed" move to next Step, then even if step1 fails the chain will move to Step2 and so on. Though the Step1 status is error. The main jobchain status would be completed.

    HTH.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.