Hi experts,

I maintained parallel sequence in ECC routing and all of the operations in both the main and parallel sequences are APO relevant.

I have maintained branch and return and referenced the main sequence in the parallel sequence.

However, when I am transferring that routing to APO, the PDS is not getting the operations from the parallel sequence.

Only operations from main sequence are getting transferred.

As per the SAP help document, the parallel sequence operations supposed to get transferred to APO as a standard functionality.

Is there anything else, I need to do, to get the parallel sequence operations in the APO PDS?

Thanks for your help.

Regards,

Manimaran M.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 01, 2016 at 10:37 AM

    Hello,

    Could you please share the screen shot of PDS activity relationship?

    Did you try CURTO_CREATE with extended consistency check?

    Please note

    When you use parallel sequences, the system generates an start to start relationship between the last parallel activity and the subsequent activity of the return operation's last activity.

    Please refer SAP note 437400 - Alternative and parallel sequences in APO integration

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Brahmankar,

      Thanks for your reply.

      I tried both RIMODINI and CURTO_CREATE with extended consistency check. No errors.

      I also cross verified all the points you mentioned. All good.

      Still the parallel sequence is not moved to APO.

      Very strange.

      Regards,

      Manimaran M.