Hi Gurus,

I am sure this already has been answered but I did not find the corre t thread. :-(

Please help! We forgot to maintain activity prices for 1 cost center and now have bookings of order conformations with 0 costs...

Now we maintained the missing activity prices but when I do the cost determination I don't get any error and costs are not updated...

Is there any standard way to revaluate these existing order confirmation?

Many thanks!

Sandra

pastedImage_0.png (13.4 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Mar 30, 2016 at 11:54 AM

    Hi Sandra

    For Production Orders it would have been easier as you can maintain actual activity price in KBK6 and then run revaluation. Am not sure if the Revaluation of PM Orders do exist. If yes, you can use that approach

    Another option is reverse and re-do the confirmations

    I wonder why and how the system allowed you to post confrmations with Zero price.. Ideally, this should have been accumulated in COFC to clear later on

    Regards

    Ajay M

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Sandra,

      There is no such thing as revaluation with planned prices.

      You cannot calculate actual prices if the system was not designed or setup to calculate actual prices.

      What you can do is:

      1. Maintain the proper plan price in KP26.

      2. Reverse confirmation

      3. Post it again, so the system will pick up the non-zero plan price this time

      Regards,

      Paulo

  • avatar image
    Former Member
    Mar 30, 2016 at 04:41 PM

    Hi aall,

    ok thanks for your help!

    I also found out that the plan activity in KP26 was created, indeed with 0 costs but it seems to be ok and the confirmation creates no error in COFC, When there is no activity planned for the combination of cost center and activity (no master record in KP26) you get an error in COFC.

    Ok so we have to reverse the confirmations....

    Thanks and regards!

    Sandra