Resource downtime in ECC PP Module

Hello Experts,

Is there a transaction code or DB table where I can find the resource down time maintained for a work center in a plant ? I could not find any in CR03 transaction code. Please let me know if there is such option in ECC PP Module.

Thanks & Best Regards,


Babu Kilari

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Mar 29, 2016 at 09:19 AM

    Hello,

    There is no functionality of resource down time in ECC. It is available in APO /SAPAPO/RES01 transaction.

    In ECC you can have available capacity which can be defined in capacity tab either by standard available capacity or by using Shift sequence (OPA4) .

    And you can assign sift sequence for specific time duration to your work center.

    Table KAKO Capacity Record and KAZY Interval of Available Capacity.


    Best Regards,

    R.Brahmankar