hello experts ,
there was a need to exports all reports out of sap system . i tried to use cg54 and used export functionality . I tried with 10 sds's and it did create order . I went into cvd1 and pulled that order . I am now seeing all 10 reports having status bundled . I am not able to change them to released or completed by accepting . the status is sitting there for quite a long time . my next step was to download those 10 reports from al11 .
please need help on this
Dear Krishna
if reports are still "bundled" in CVD1 some set up is missing for report shipment (some events are missing and some reports are not running properly).
Please check the corresponding OSS note (for set up of SDS shipment). Any event and ABAP report which must run is explained. WWI must be up and running.
C.B.
PS: may be read: Process Report Shipping
and
Add a comment