Hi All,
Need your help ton below issue
In resource master -> Capacity profile we have maintained the start and end time day wise. No shift and sequence is allocated to resource.
For ex - Monday - Friday- 6am to 15 Pm etc.
Expectation - Ds board should show time 6am to 15 pm as working time remaining time in gray.
But it is not happening in DS , DS board is showing different result than expectation.
Please let me know the other time source which is fetching/impacting by Ds board and showing the result.
Rgds
SDB
Suren,
Since you can see planning version in the capacity profile, you have the right settings. Another place to check would be the Planning Board profile for your DS Board, resource chart and see if "hide non-working times" is checked.
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks abhishek.
@Rupesh - Issue resolved thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Suren,
Make sure you updated the resource master capacity profile for planning version '000'.
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.