on 02-07-2017 6:55 AM
By mistake our customer has started an org.unit (HRP1000) too early. They want to change the begda to a later date. However, we are stopped by the Time Constraint. Any suggestions to change the date? (We cannot play With TC, as we have several thousand end users in our system).
Best regards
Kirsten
Thank you - the report works.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please try using report RHBEGDA0. You can do some test run in your test system and check is it suits.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am always concerned with direct database updates.
But if you feel that is safe for HRP1000, I might as well change it from edit-mode in SE16N
Regards
Kirsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
write a small report:
read record from HRP1000 directly from database
delete record from database
change BEGDA of record in report
write record back to database
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.