By mistake our customer has started an org.unit (HRP1000) too early. They want to change the begda to a later date. However, we are stopped by the Time Constraint. Any suggestions to change the date? (We cannot play With TC, as we have several thousand end users in our system).

Best regards

Kirsten

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Volker Binder Feb 08, 2017 at 07:59 AM
0

write a small report:

read record from HRP1000 directly from database

delete record from database

change BEGDA of record in report

write record back to database

Share
10 |10000 characters needed characters left characters exceeded
Kirsten Bølling Feb 08, 2017 at 10:03 AM
0

I am always concerned with direct database updates.
But if you feel that is safe for HRP1000, I might as well change it from edit-mode in SE16N

Regards

Kirsten

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Feb 08, 2017 at 10:14 AM
0

Please try using report RHBEGDA0. You can do some test run in your test system and check is it suits.

Share
10 |10000 characters needed characters left characters exceeded
Kirsten Bølling Feb 09, 2017 at 08:34 AM
0

Thank you - the report works.