By mistake our customer has started an org.unit (HRP1000) too early. They want to change the begda to a later date. However, we are stopped by the Time Constraint. Any suggestions to change the date? (We cannot play With TC, as we have several thousand end users in our system).

Best regards

Kirsten

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thank you - the report works.

former_member226203
Active Contributor
0 Kudos

Please try using report RHBEGDA0. You can do some test run in your test system and check is it suits.

Former Member
0 Kudos

I am always concerned with direct database updates.
But if you feel that is safe for HRP1000, I might as well change it from edit-mode in SE16N

Regards

Kirsten

former_member226519
Active Contributor
0 Kudos

write a small report:

read record from HRP1000 directly from database

delete record from database

change BEGDA of record in report

write record back to database