The in-process inspection lot where the usage decision is accepted and lot has been cancelled unfortunately . Due to this the Production order closing cannot be completed .
please do provide the solution how to reverse the usage Decision and Status Reset for the same inspection lot .
The Error Displaye "inspection Lot "XXXX"for order "XXXX" does not have required status.
Please do provide solution for closing the production order.
Thanks and Regards.
Vishnu Ravi.
Go to QA12 enter inspection Lot, from menu bar usage decision >Function>Reset cancellation
and SAVE
Thanks