PP-PM integration

Former Member
0 Kudos

Hi

PP-PM integration

Our requirement is, at the time of production

confirmation using transaction code C011, or MFBF system has to cumulate the confirmed production quantities and when it reaches certain quantity (Ex: 100 tons).

After crossing the 100 tons, system should generate the maintenance order in plant maintenance.

We need a maintenance order on particular equipment.

How to map this requirement?

Regards

KSA

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi sukhbir,

thank you for giving solution,

Sucess and regards

ashok varma

0 Kudos

Hello Ashok, Sukhbir

We have started a new Forum for "enterprise Asset management" topic. If you think useful you may post messages for Asset management related topic to that forum.

Regards

Hemant

Former Member
0 Kudos

Hi

Hemanth,

thank you for the helful answer,I will go through the document.

If you have any screen shots document which you worked earlier on this scenario ,please send me.

I also work out on this.

so far ihaven't worked on PRTs.

Actually at my client place i got this requiremnt.

ok thank you for sending the document n helping me.

Success and regards

Ashok Varma

Former Member
0 Kudos

Dear Ashok

In the PP you should define an equipment say weighing balance for the order. Then create a char under the equipment for the mesauring document as counter, define maint plan based on counter with strategy that after 100 tonnes, a maint order is required. keep recording in the counter and once it reaches the counter above the 100, schedule the plan and maint order get generated. Thats how I used to do

Regards

Sukhbir

0 Kudos

Hello KSA,

As I understand you can create Measurement document for all PRT used in production order basd on the confirmation created in CO11.

You can define the perormance based PM plans to take care of your maintenance needs. Refer following link in the help docment site of SAP so that you get more detailed idea on this topic

http://help.sap.com/saphelp_erp2005/helpdata/en/89/a42781461e11d182b50000e829fbfe/content.htm

Please note that this functionality in not avaialble in the Process orders

Take care..

Regards

Hemant