Hi ,

I have One requirement where we need to schedule the channel for  2nd working  day of every month.Monthly once running Status

Suppose 2nd day is Wednesday for March Month.

but in April Month 2nd day is Saturday but it should start on Monday.

How can I get this requirement Please help on this.

Regards

Umesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member186851
Active Contributor
0 Kudos

Hello Umesh,

How you decide the second day??the working day will be second?

umesh_badveli
Participant
0 Kudos

Hi Raghuraman

Its 2nd Working day of every month

Regards

Umesh

former_member186851
Active Contributor
0 Kudos

Hello Umesh,

In the ATP select Monthly option,Then select 2nd Day of every month option.

umesh_badveli
Participant
0 Kudos

Hi Raghu

thanks for reply ,you are not getting my point it should be 2nd working of month ..

For example Take this Year ,

March 1st day is Tuesday,2nd day is Wednesday it should run on 2nd working day.

For  April 1st day is Friday ,2nd 3rd day are Saturday and Sunday its week off channel should run on 4th day it is Monday it is second working day of month April Month.

Please let me know if you have any idea on this .

Regards

Umesh

former_member186851
Active Contributor
0 Kudos

Hello Umesh,

In your case then you should configure mutliple ATP for every month,Select the date based on working day.