Consider Alternative PPM/PDS‏

Dear Expert ,

I have many PPM's with different resource and during the overload for PPM1 I want the optimizer to move to the next alternative PPM2 and so on ...

I tried to achieve this by PPDS heuristic but not success , and now with optimizer , could you please assist


Regards


Rami

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Mar 25, 2016 at 04:54 PM

    Hi Rami,

    A possibility in this case is to create quota arrangements in /SAPAPO/SCC_TQ1. There, you can define quota for each item/PPM as required. Then, you can run SAP_PP_Q001, which will distribute the shortages among the valid quotas/PPMs.

    If you have a very simple PPM/PDS, the Wave Heuristic (SAP_REM_002) is an option. You can find details in note 584051 Multiresource planning (primary resource) (documentation)

    It is also possible to use BAdI /SAPAPO/PWB_SOS, Method PWB_USEX_SOS. Whenever heuristic is creating an order, it executes source determination to find what are the valid sources and rank them (e.g. according to procurement priority, etc). In this BAdI Method, you can change the source ranking such that another source will be chosen.

    PP/DS Optimizer and DS heuristic will not change the source of supply (PDS/PPM) of a given order. If the scenario is modelled such that there is a single PPM/PDS with alternative modes, the optimizer and/or DS heuristic may be able to reschedule the activities into alternative modes in case of missing capacity.

    Regards,

    Tiago

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 27, 2016 at 05:23 AM

    Rami,

    I suggest you first read SAP help on Source determination.  There are several logical methods available to you to rank the priorities of the various sources of supply (which include PPMs).

    Determination of Source of Supply Ranking List - Source Determination - SAP Library

    Best Regards,

    DB49

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 25, 2016 at 12:09 PM

    Dear Rami,

    In Order to consider the next suitable PPM/ PDS  we are also having an additional functionality of Planning Id in Production versions. When we use the planning Id while creating the production versions in ECC and selection method which is available in MRP4 . We can prioritize the PDS.

    Hope this clue would help you.Rewards are highly appreciated.

    Thanks & Regards

    Arvind Pabba