02-19-2016 10:23 AM
hi
how this scenario can be worked out
full installation of meter on 01/02/2016
full removal of meter on 01/02/2016
reversal of removal on 01/02/2016.
is it possible.
Message was edited by: William Eastman
03-16-2016 9:09 PM
supplying activity date 01/02/2016 for removal should raise EN015
check the actual dates in egerh & eastl
likely the removal activity date is 02/02/2016 (this will show valid from / to as 01/02/2016 however)
reverse technical removal & do a billing install to revert to currently installed.
03-16-2016 9:09 PM
supplying activity date 01/02/2016 for removal should raise EN015
check the actual dates in egerh & eastl
likely the removal activity date is 02/02/2016 (this will show valid from / to as 01/02/2016 however)
reverse technical removal & do a billing install to revert to currently installed.