Heuristic run in Background : Missing demand coverage

58 Views

Hi All,

Need help with the below issue.

For some products, Heuristic run in Background[in Batch job] does not plan[basically the STO planned Orders were not created ] or sometime does not cover the demand completely. When we run it manually the product is planned completely.

PFA the settings that we are passing in the Run.

What could be the possible situations in which this issue might occur or is there a none SAP note for this. Our SCM version 5.10.

Regards,