I have a cost center that is collecting costs for another cost center, in another company code.  We are all within the same controlling area so it is not an issue to do a distribution of costs at month end from one cost center to the other.

The question I have is this:  In order to capture and monitor some of the costs they have now opened an internal order against the first cost centre.   Naturally these costs settle each month, and against the cost center.  But the distribution does not pick them up to move the costs to the second cost center.

How can I get this internal order to distribute/settle to the second cost center?  Does it have to be within the internal order?

ie:  order  201524

Settlement to Cost Center 5700

All costs in 5700 get distributed to 61010 at the end of each month.

Now with these items settled against the internal order, they are excluded from the distribution.

Next steps are:???

Accepted Solutions (0)

Answers (3)

Answers (3)

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi Ellen

Why not you settle it directly to final cctr ?

Kamal

ajaycwa1981
Active Contributor
0 Kudos

Hi Ellen

I earnestly request you to close your threads. None of them are closed. You can close by marking the relevant answer as CORRECT ANSWER. if there is no solution close the thread by marking ASSUMED ANSWERED.

It will help others in future to know the solution. Hope you will do your bit for a better Scn

Ajay M

ajaycwa1981
Active Contributor
0 Kudos

Hi Ellen

When you settle the internal order, do you settle by primary cost element or using secondary cost element?

note that distribution cycle csn handle only Primary cost elements.

second point to check is you must settle the order before the distribution cycle is executed.

You can also settle the order to the end cost centre if possible