Cost planned of internal activity on network not shown on cost center

Feb 06, 2017 at 01:28 PM

47

avatar image

Hi Experts,

I'm trying to solve an issue connected with network planning.

I have a project with WBS (with flag integrated planning) and network. All flag "integrated planning" are set in CO customizing.

I'm planning activity cost at internal operation level.

When I run S_ALR_87013543 report I can see the cost of the planned activity. I want to credit with this cost the relative Cost Center.

After that, I run CJ9QS to copy the planned activity cost to the other CO version. I do this and everything seems ok.

But when I try to run the report S_ALR_87013611 to check if the cost is charged to the relative cost center, no cost are visible. What I'm missing?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Yuri Orlov Mar 15, 2017 at 07:19 PM
0

Hello Stefano, i assume it's a report layout problem.