SNP planed order are not created

Former Member
0 Kudos

Dear

I have a problem that after run SNP heuristics(location/network/multi-level),there are no planed order are created.

( not all,only 1 product are not created planed order,so PB setting and marco is ok)

I check lot size of product master ,and PDS,there is no problem.

Would you have some ideas about this issue?

Thanks & Regards

Ellen

Accepted Solutions (0)

Answers (3)

Answers (3)

ruchi_das2
Active Participant
0 Kudos

Hi Yuan,

Can you start by running location heuristic in the standard Planning Book / Data View 9ASNP94 / SNP94(1). If you do not see anything in total receipts after the location heuristic runs, you should try manually entering vales in Distribution Receipt(Planned) , Save and then check the order details to see if the source of supply if your PDS etc.

Regards

AK

marianoc
Active Contributor
0 Kudos

Hi Ellen,

Try to create a planned order manually in RRP3. You should get an error with the explanation of what is missing.

Kind Regards,

Mariano

former_member187488
Active Contributor
0 Kudos

Hi Mariano,

Sorry but I don't think this could help. PPDS and SNP follow totally different logic.

BR, Ada

marianoc
Active Contributor
0 Kudos

You are right Ada. I did not read that it was SNP heuristic.

In this case, try to create the order in the planning board manually.

Kind Regards,

Mariano

Former Member
0 Kudos

Additional

There are several demands and have no enough stock.

So it needs planed order for demands.

But now no planed order are created now.

former_member187488
Active Contributor
0 Kudos

Hi Ellen,

For this issue I can list tens of possibilities.
Of course we can make some guesses here but as per my experience only debugging could help to identify the root cause.

BR, Ada

Former Member
0 Kudos

Hi Ada

Thanks for you suggestion.

Maybe we have to debug to fix the problem.

Regards

Ellen