Application Development Discussions
Join the discussions or start your own on all things application development, including tools and APIs, programming models, and keeping your skills sharp.
cancel
Showing results for 
Search instead for 
Did you mean: 

BADI ME_PROCESS_REQ_CUST Not Trigger.

Former Member
0 Kudos

Dear Experts,

I write code in BADI ME_PROCESS_REQ_CUST.  it doesn't contain any error.

i activate Badi with breakpoint. but it not trigger when  i go through MD04.

i want to  debug BADI for the same MD04 for automatic PR generate from MRP.


Thanks And Regards,

SAM.

1 ACCEPTED SOLUTION

raymond_giuseppi
Active Contributor
0 Kudos

Did you look on OSS notes, there is a KBA on BAdI for MRP:  2012620 - MRP: Problems with BAdIs

Hint: AFAIK this BAdI is related to the PR Enjoy transactions so may be not executed, nevertheless set "update debugging" on. Also ,check documentation at SPRO : Production, Material Requirements Planning, Business Add-Ins for Requirements Planning. (a ME BAdI on a MD transaction)


Regards,

Raymond

1 REPLY 1

raymond_giuseppi
Active Contributor
0 Kudos

Did you look on OSS notes, there is a KBA on BAdI for MRP:  2012620 - MRP: Problems with BAdIs

Hint: AFAIK this BAdI is related to the PR Enjoy transactions so may be not executed, nevertheless set "update debugging" on. Also ,check documentation at SPRO : Production, Material Requirements Planning, Business Add-Ins for Requirements Planning. (a ME BAdI on a MD transaction)


Regards,

Raymond