on 01-28-2016 4:17 PM
Gurus:
I'm trying to setup a hierarchy on my resources in /sapapo/relhshow. I'm looking to have 4 levels (I have setup the config to allow 10 levels for future expansion). My first level is plant level. My 2nd level is Group1. My 3rd level is SubGroup1. My 4th level is at the actual real Resource.
When I add orders in APO SNP and then go to look at the capacity on the Resources, I get a capacity requirement on my 4th Level (actual Resource) and on the 3rd Level (SubGroup1), but I do not get capacity requirements on my 2nd or 1st Levels up.
I attached a screenprint. Does anyone have any ideas? I asked 2 external consultants and they think my setup is correct, so they cannot explain why I wouldn't see capacity requirements on Level 1 and 2 (the 2 highest grouped up levels).
Best Regards,
Andrea
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Andrea,
See if the note 1568018 helps.
Thanks, Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I put a ticket in with SAP and they told me standard functionality will only support two levels. I am a bit disappointed as it lets you build as many levels as you setup in config, but will only display the aggregated capacity requirement up to the 2nd level. I haven't been able to get an explanation from SAP as to why you are allowed to configure other levels. I didn't want planning to run on those other levels, I just wanted to use the higher up levels to display a total of the capacity requirements from the real work centers at the lower levels.
Andrea
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.