PR not generated for Manual reorder point planning

Hello All,

I have an issue regarding Reorder point planning. PR is not generating if a open PO or PR is present. This PO is created manually with reference to PR. If i delete the old PO and PR only then new PR is generated after i run MRP in MD02

I have maintained following details

  • MRP type VB and lot size HB
  • ROP=45 PC,Maximum stock level = 200 PC and safety stock = 10 PC
  • Planned delivery time 10 days and availability check = 02
  • Delivery date of the PO is present inside the Planned delivery date of material master.

Desired Result: PR Qty = 160 qty

I have refereed many threads.but in this tread the correct out put is shown and i have followed the same things.

https://archive.sap.com/discussions/thread/3221011

Note:

I have attached screen shots for reference.

oppj-for-checking-rule-pp.jpg

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 06, 2017 at 12:11 PM

    Reorder point 45

    Stock on hand 40

    open PO 10

    new total 50, which is above ROP 45 and so you don't get a new requisition.

    See also OSS note 1974398 - MD04: Available Qty lower than reorder point and safety stock