I came across a scenario like below,pls share some input to map in the system.
Need to do some Assembly/production process for our sister concern
sister concern will send the materials for assembly with some component with a subcontracting po
Assembly need to happen in the plant and need to capture the manufacturing cost and any other additional raw material used other than subcontracting po.
So is it possible to map this scenario by MTO? then how the cost will be send back to sister concern
request some details explanation from expert
Regards,
Abu.
Hello
This is called job work in SAP. As the material belongs to your sister concern company (Separate company code) it should not be valuated in system so all those material are created as non- valuated articles.
Create Sales Order for Job work quantity with expected finish material,(e.g. JOBFERT) the suppled material by customer will be inward in system through 501-E with reference to sales order. This material stock will appear in system as special stock.
Production order is created for JOBFERT. The supplied material is consumed along with your own material in addition of production activities. In this case the cost of your own material and activities will get booked for this production order and further to sales order.
The manufactured material will be dispatched to customer against created sales order. You can maintain the gross price in condition record as per your cost calculations.
Regards,
Shekhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.