Dear Experts,
Please help me understanding the control PR generation in production order.
I want to create PR through producion order with control key pp02 after release of particular operation. To achieve this i have maintained configuration as follows:
In OPL8 - Reservation Relevance/Generation of Purchase Requisition is selected as 2 (on release)
Still system creates PR immediately after saving production order with Reservation Relevance/Generation of Purchase Requisition field as 3
kindly suggest any other config required.