Dear All,

I need your help regarding Third party scenario with sub contracting via sales order. I have searched many blogs and posts but not got proper reply.

Business requirement is to do subcontractor suppose to send finished goods stock directly to customer.

Steps we have followed:

1. Created sales order with internal order assignment(account assignment tab) through which PR gets generated in the background.

2. PO created with reference to PR with account assignment category as ' X' and item category as ' L'.

3. Transfer material to vendor via 541 - ME2O.

4. MIGO done. But the finish material stock got consumed against internal order.

How can we do outbound delivery as there is no stock in storage location? How to transfer finish goods directly to customer?

As we have used account assignment ' X' in PO because of which stock gets directly consumed. Is there any way to bring stock in storage location?

Thanks,

Priti.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Ajit,

In my case material is externally procured so I m trying with account assignment cat as "x". please suggest on this front.

Thanks

Priti.

ajitkumar
Active Contributor
0 Kudos

I think if you use any account assignment category with consumption posting V, it will get consumed in the order with the order as the cost object and the order augmented with the cost.

probably you should test with M. You may need to do some settings for that, following the error messages you get.

I have never worked with sale order costing, so cant give you any specific inputs.

Former Member
0 Kudos

Hello All,

Any response plz.. when I am using standard PR and PO types, system is giving error for the combination of document type of PR/PO and itemcategory of PR/PO.

Can anybody please help me in subcontracting+ third party scenario.

Regards,

Priti.

Former Member
0 Kudos

Hi Priti,

Please check if the quantity update is activated for the given material type.

Regards

Sesha

Former Member
0 Kudos

Hi,

We just need to know how to do Goods receipt and get material in storage location so that stock can be sent to customer through PGI and virtual outbound delivery.

Thanks

Priti

ajitkumar
Active Contributor
0 Kudos

Why are you using internal order as account assignment

Isn't it normally E or M as account assignment from Sale order depending on whether sale order is cost collector

pl check the below link on account assignment category in product costing

https://help.sap.com/saphelp_46c/helpdata/en/97/f42c7dd435d1118b3f0060b03ca329/frameset.htm

Former Member
0 Kudos

Hi,

Any response...? Just want to know how to create GR so that material comes in stock and outbound delivery can be done..

former_member233510
Active Contributor
0 Kudos

Please check the business function LOG_MM_OM_2. Through this function you can process third-party order for subcontracting. For more details, please check the following link.

LOGMMOM2_DS