Question about DAP.

Hi, All

I have a problem to create data archiving process for NLS Test.
I created the DB connection and verified the success.
- DBCO
- ADBC_TEST_CONNECTION

But when I tried to create data archiving process, the menu is not shown like below.

Are there any additional prerequisites for DAP Test?

Best Regards,
Gi-Sung Jang

capture.jpg (118.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Feb 07, 2017 at 02:09 PM

    Hi Gi-Sung Jang,

    You have to configure Near-Line connection as well. Execute transaction RSDANLCON and fill the required entries.

    http://www.sap.com/documents/2013/03/d2ff3a4c-577c-0010-82c7-eda71af511fa.html page-82.

    Regards,

    Amit T

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 08, 2017 at 09:48 AM

    ideally DAP menu should be there even before configuring NLS. I would suggest try restarting your SAP instance and check.

    Please share latest screenshot of RSA1> InfoProvider menu.

    Regards,

    Amit T

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 09, 2017 at 05:25 AM

    Hi, Amit

    When I execute "RSA1", The following error is returned.

    I attached the error trace file.
    I can't get the screen because of this error.

    Please help me to solve this problem.
    error.txt

    Best Regards,
    Gi-Sung Jang

    Add comment