Hello All,

i have copied a planning area A to B, now all the data what i have in planning area A is in planning area B.

Now, for planning area B, i want to change MPOS name.

is it possible to change the MPOS name here  for planning area B ? Please help me with relavant soultion.

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

alok_jaiswal
Contributor
0 Kudos

Hi Neehal,

You assign a planning area to a MPOS, which in turn is assigned characteristics and aggregates. Since your planning area is based on an existing MPOS, you won't be able to change the MPOS name in planning area created.


If you want your planning area to be based on new MPOS, the you have to deinitialize the planning area, delete the time series data and then have it based on new MPOS.


Regards,

Alok