on 01-14-2016 11:35 AM
Hello Experts,
I create a strategie with 22 cycles, but in the task list I only see 20 cycles I don't knw why ??!!!
Thank you for your help,
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mika
Click on Maintenance package icon to enter the package.
In the screen you have option to enter only 20, you need to select the operation and click maintenance package to enter more than 20.
Regards
Terence
Hello Maria,
Is there a possibility to show the other cycles ?
Hi Mika,
You can check only by individual operation. You can display only by 20 packages.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.