Which table to refer routing opration activity Time in SAP PP

Business uses transaction (Customize)

to review actual operation confirmation times. This is the actual time the employee has spent on that particular operation and activity.

The business is requesting an enhancement to the report to add the routing operation activity times to the report.

SETUP – MACHINE – LABOR - REWORK

Which table should I refer to add routing activity types to report " Please Help , As I am New to SAP

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2016 at 04:08 PM

    Nikhil,

    Hmmm.

    I am New to SAP

    Ok, we all have to start somewhere....

    Business uses transaction (Customize)

    Not sure what this means, but I have to assume this is represents some customized ABAP program. Since you are new to SAP, you have little functional knowledge, and presumably you have no technical knowledge, and you are stumbling around in the dark. You should speak to your supervisor, and tell him/her what your situation is, and ask for guidance.

    If you decide instead to persist in trying to solve this yourself, then search in the SCN forums (that little box at the top right of this screen) to find the tables you seek. This question already asked and answered many times.

    Best Regards & Good luck,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 11, 2016 at 02:16 AM

    Hi Nikhil,

    I guess you want to know which table contains routing operation information, you can check table PLPO.

    Br, Nancy

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 11, 2016 at 06:11 AM

    Hello Nikhil,

    first pass the material and plant in MAPL and get the Group and Group counters

    similarly pass this group and group counter in to PLPO you will get the standard value keys i.e. activities

    Regards,

    Venkatesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 17, 2016 at 01:59 PM

    Thanks All For your guidance ,I am able to add routing operation activity time using PLPO table.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.