on 01-05-2016 8:54 AM
Hi Experts,
Currently we are having DEV,QA,PROD systems of PI.Our client wants to make a fresh Pre production system for PI.Can anyone please help what are the necessary action items we have to perform for PI to achieve the Pre produciton in PI.
Regards,
Shaik
Hi Shaik
Below are some of the action items
1. You have to import all the IR objects from Dev. Create separate transport request for each s/w component.
2. Create the business system for preprod in SLD , then map the same as a target buisness system in SLD.
3. Import the integration directory objects.Then update the communication channels with appropriate connection parameters.
4. Maintain value mappings in ID.
Thanks,
Indrajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Indrajit,
Thank you very much for the prompt reply.
Object transporting all is doing by BASIS team. Any mapping issues will come after importing the objects and also they did some value mapping and UDF's in some interfaces.
How can i maintain the value mappings in ID.
Please give some idea.
Regards,
Shaik
Hello Shaik,
In addition to Link shared by Inaki,You can refer the below as well
System Copy - Technical Operations Manual for SAP NetWeaver - SAP Library
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Shaik,
May be it would be quicker to do a system copy, check this note 1299373 - Configuration Wizard: PI System Copy
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.