After MD02 mrp run, scheduling agreement not be generated,- urgent

Former Member
0 Kudos

Hi all

New year greetings,

I am requesting  this second time,

After MRP run MD02 - scheduling agreements not being  generated.

Maintained all parameters correctly, such as.,

Me01 - source  list - SA Number with item , and 2 , souce list validity etc..

Me33L - SA validity also correct.

MD02  parameters also correct

Still not generating SA    after MRP run.

I have compared with other materials also.

PLease help.

It is very urgent.

Thanks and Regards

R. Manikandan

9677289450

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member185450
Active Contributor
0 Kudos

Hello Mani,

Could you please share your ME32L screen shot

similarly ensure the MRP Group has been assigned for that material and the document type and MRP Group combination has been maintained in the OPPR

Regards,

Venkatesh..

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I'm the moderator of the PP space and, since you are a new user, I would like to ask you to check the and the blog .

You should also consider that SCN is not a forum for ordering free technical consulting. It is a collaborative community where people voluntarily help you to understand things better in the SAP world. So please avoid words such as "URGENT" and formulations like "answer asap" and "please send step by step description".

Regarding your issue, I suggest you to consider point 1 of the document .

BR
Caetano