on 12-31-2015 12:06 PM
Hi sir
i faced a problem when we checked the material change we found planned delivery time changed with out change document as below from t-code AUT10.
planned del.time changed from 1 to 113 at 08072013 and changed again from 113 to 130 at 21092015 at the end PDT changed from 175 to 135 day
i ask why there is no any change document from 130 to 175
If material changes are done with direct input RMDATIND then the user can decide if he wants to write change documents or not. So this report might be a source for a missing change document, but it could also happen thru direct table updates from ABAP reports and other tools which are propagated especially in SCN from unexperienced users who work in unsecured environments.
Change documents are usually written with manual changes, if the changes are done by SAP programs based on desired actions then you usually do not get change documents (e.g. an update of the moving average price with a goods receipt)
In a retail environment is a transaction WPDTC to calculate the planned delivery time, as I am not in Retail, I don't know if this transaction writes change documents, but it could be a potential source too.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check the layout, whether you've document number in the displayed columns.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.