Dear FM Gurus,

Currently, we have integration between Project System and Fund Management. Availability Control activated in FM only, and i have activated derivation for WBS Element from Network via Function Module FMDT_READ_ORDER_NP_FROM_FMZUOB, but when i try to release network from CN22, WBS Element not derived from Network, is there any solution for this problem? please let me know

Regards,

Angga Saputra

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Dec 29, 2015 at 08:58 AM

    Hi,

    I'm not sure what you are doing in FMDERIVE, but keep in mind that you can derive only FM objects, while WBS is not an FM object. Though, visually available as target field in FMDERIVE, it won't be 'substituted' by your derivation logic. WBS should come from the original document itself.


    Regards,

    Eli

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 30, 2015 at 01:06 AM

    Hi,

    I have experience on the integration with Project System and Fund Management. May i know do you maintain this derivation in FMDERIVE and to which FM objects.

    From my previous project experience we derive the WBS to the Funded Program.

    Regards.