on 12-23-2015 4:04 PM
Hi All,
I need help with understanding the date being calculated here by system. After planning, system created SNP Planned Order with Availability date and 04/07/2016, but the End date for the Planned Order is 30/06/2016.
What could be the possible entities that might be influencing this deference in dates.
Please see the attached screens.
Regards,
Avinash
Hi,
Apart from GR processing time; check the bucket offset setings in PDS/PPM or in optimizer profile. If it is not equal to 1.0 (is close to 0) the availability date will be shown as next day. If it is 1.0 it will show same availability date.
Nitin Thatte
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Avinash,
Can you please check if you have a GR processing time maintained for this location-product. The difference between the start date and end date would be from the PDS for manufacture the product and the GR processing time is the lead time added to the end date to determine when the product is available.
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.